As of 17th August 2022, Countryside Stewardship Agreement holders have been issued a blanket derogation on specific options that will enable them to graze and cut areas previously restricted under the Environmental Schemes. The temporary lapse, is in response to lobbying from the NFU and other farm focused organisations as the on-going drought throughout the UK creates grazing and forage shortages.
Eligibility The blanket derogations have been applied to options in Mid- Tier and Higher- Tier Countryside Stewardship, Higher Level Stewardship and Entry Level Stewardship.

The options below are subject to the derogation. Agreement holders do not need to contact the RPA if they carry out any of the permitted temporary adjustments but are required to complete a Temporary Requirement Adjustments Form and keep it on record.

Those with options and actions that fall outside of the tables beneath should still seek permission from the RPA before deviating from the management prescriptions as written within your Agreement Document. Please contact your consultant for help in seeking temporary amendments beyond those detailed below.

Affected Countryside Stewardship Options
| Option Code | Option Title | Temporary Permitted Adjustment |
| GS1 | Take Small areas of out of management | Cut or graze from 17th August |
| GS2 | Permanent Grassland with very low inputs (Outside SDA) | Supplementary feeding including hay, silage and energy blocks in permitted from 17th August where necessary to prevent animal welfare issues. Steps must be taken to ensure the sward is not damaged where possible, for example move ring feeders regularly. |
| GS10 | Management of wet grassland for wintering waders and wildfowl | Supplementary feeding including hay, silage and energy blocks in permitted from 17th August where necessary to prevent animal welfare issues. Steps must be taken to ensure the sward is not damaged where possible, for example move ring feeders regularly. |
| OP4 | Multi Species Ley | Cut or graze up to 100% of area from 17th August |
| AB1 | Nectar Flower Mix | Cut or graze from 17th August |
| AB8 | Flower Rich Margins and Plots | Cut or graze from 17th August |
| AB13 | Brassica Fodder Crop | Cut or graze from 17th August |
| AB15 | Two Year Sewn Legume Fallow | Cut or graze up to 100% of the area from 7th August |
| BE1 | Protection of in-field Trees on arable land | Cut or graze from 17th August |
| BE2 | Protection of in-field trees on intensive grassland | Cut or graze from 17th August |
| SW1 | 4-6 M Buffer strip on cultivated land | Cut up to 100% of buffer strip from 17th August (no grazing) |
| SW2 | 4-6 M Buffer strip on intensive grassland | Cut or graze up to 100% of buffer strip from 17th August |
| SW3 | In- field grass strips | Graze from 17th August |
| SW4 | 12 – 24 m watercourse buffer strip on cultivated land | Cut up to 100% of buffer strip from 17th August (no grazing) |
| SW7 | Arable reversion to grassland with low input fertiliser input | Graze until 31st October |
| SW8 | Management of intensive grassland adjacent to a watercourse | Graze until 31st October |

| Option Code | Option Title | Temporary Permitted Adjustment |
| EC24 | Hedgerow tree buffer strips on cultivated land | Cut or graze from 17th August |
| EC25 | Hedgerow tree buffer strips on grassland | Cut or graze from 17th August |
| EE1 | 2m Buffer strips on cultivated land | Cut or graze from 17th August |
| EE2 | 4m buffer strips on cultivated lane | Cut or graze from 17th August |
| EE3 | 6m Buffer strips on cultivated land | Cut up to 100% of buffer strips from 17th August |
| EE4 | 2m Buffer strips on intensive grassland | Cut up to full strip width from 17th August |
| EE5 | 5 M buffer strips on intensive grassland | Cut up to full strip width from 17th August |
| EE6 | 6 M buffer strips on intensive grassland | Cut up to full strip width from 17th August |
| EE9 | 6m Buffer strips on cultivated land next to a watercourse | Cut up to full strip width from 17th August |
| EE10 | 6m Buffer strips on intensive grassland next to a watercourse | Cut up to full strip width from 17th August |
| EF1 | Management of field corners | Cut or graze from 17th August |
| EF4 | Nectar Flower Mix | Cut or graze from 17th August |
| EF6 | Overwintered Stubble | Sow forage crops on up to 5ha in 10 ha (50%) and graze until 14th February 2023 |
| EF15 | Reduced herbicide cereal crops followed by overwintered stubble | Sow forage crops on up to 5 ha in 10 ha (50%) and graze until February 2023 |
| EF22 | Extended overwintered stubble | Sow forage crops on up to 5 ha in 10 ha (50%) and graze until 14th February 2023 |
| EJ9 | 12 M buffer strips for watercourses on cultivated land | Cut up to full width from 17th August (No grazing). |
| EK1 | Take field corners out of management | Cut or graze from 17th August |
| EK3 | Permanent Grassland with very low inputs | Supplementary feeding including hay, silage and energy blocks in permitted from 17th August where necessary to prevent animal welfare issues. Steps must be taken to ensure the sward is not damaged where possible, for example move ring feeders regularly. |
| EL1 | Take field corners out of management in SDAs | Cut or graze from 17th August |
| EL3 | Permanent Grassland with very low inputs in SDAs | Supplementary feeding including hay, silage and energy blocks in permitted from 17th August where necessary to prevent animal welfare issues. Steps must be taken to ensure the sward is not damaged where possible, for example move ring feeders regularly. |